New RMHS: Finally...
Jul. 30th, 2007 01:50 pm![[personal profile]](https://www.dreamwidth.org/img/silk/identity/user.png)
By way of the RMPTSA newsletter:
Finally? Heh. Demolition of the old building was supposed to be earlier this month. Guess that's not happening yet...
November 2007: We begin to install classroom furniture and new equipment. During designated times, certain staff will be allowed to transport items to the new facility.
December 20 and 21, 2007: School will be closed for students to allow the staff the necessary time to establish themselves in their new teaching areas.
January 2, 2008: There will an Open House for students. The school will organize a series of building tours to acclimate students to the new building.
January 3, 2008: Classes resume in the new building.
Finally? Heh. Demolition of the old building was supposed to be earlier this month. Guess that's not happening yet...